  I&C Renovation Project of TACOA Power Station
  TACHIBANA-WAN of Electrical Power Development Company(J-Power)
  HEKINAN of Chubu Electric Power Company
Advanced Service Packages
Ergonomic Design Development of Control Room
Unified operation of multiple units
Site Search


Thermal Power
  Home > Thermal Power > Services & Maintenance >

I&C Solution Services

 

I&C Renovation Project of TACOA Power Station


 

Introduction

 

  Toshiba has won an EPC (Engineering Procurement Construction) contract from EDC (Electricidad de Caracas) to comprehensively renovate I&C (Instrumentation & Control) system of TACOA P/S Units 7 to 9 in Venezuela.
More than 20 years have passed since the TACOA P/S took over. The existing control system for TACOA P/S is an outdated system composed of electrical one-loop controller, pneumatic controller and the operation panel that consists of the hard-wired parts, such as switches, lamps, relay and analog circuits. This large-scale I&C renovation project provides various advantages and the best solution for the existing system.

 

Plant Overview
    Customer: Electricidad de Caracas (Venezuela)
Plant: TACOA CRZ Power Station

 

 
- Units 7, 8 & 9 3x460MW
- Taking over Unit 7: August 1979
  Unit 8: October 1979
  Unit 9: November 1981
- Turbine, Generator: TOSHIBA
- Boiler: MHI


Plant Overview

 

Scope of Work

 

  This I&C renovation covers Units 7, 8 & 9 and common equipment for each unit, and the scope is as follows.
  • Replacement the existing control system with our latest DCS "TOSMAP-DSTM"
  • Modernization of operator working space such as chief supervisor room and central control room
  • Replacement MT/BFPT MHC with D-EHC
  • Modernization of D-AVR, TSI and Field Devices
  • Training Simulator System
Replacement the existing control system --> Replacement the existing control system
Replacement the existing control system

 

Plant Outage Plan

 

  Plant Outage Period: 3 months
  Unit 9: July 1 to September 30, 2003
Unit 8: January 1 to March 31, 2004
Unit 7: July 1 to September 30, 2004 (including Common System)

 

Benefits of I&C Renovation Project

 

  This I&C renovation project provides the best solution for the following requirements.
  - Life extension of I&C system
- Maintenance cost reduction
- Operator work load reduction
- Reuse of existing central control room space

  Solution for life extension of I&C system
  (a) Application of TOSMAP-DSTM
  - State-of-the-art distributed control system
- Latest technologies and defacto standards
(b) Governor system modernization
  - More details about "Governor system modernization"
(c) Replacement by the latest field devices

  Solution for maintenance cost reduction
  (a) Provision of the same series of control systems including D-EHC and D-AVR
(b) Reduction of consumables

  Solution for operator work load reduction and reuse of the existing central control room space
  (a) Integration of unit control & monitoring
  - More details about "Integration of unit control & monitoring"
(b) Modernization of central control room
  - Ergonomics design based on human engineering
  - More details about "Modernization of central control room"
(c) Hybrid Simulator System
  - Operator training using simulator system
(d) Expansion and improvement of plant automation
  - Improvement of interlock and modulating control

  Solution for reuse of the existing central control room space
  (a) Ergonomics design based on human engineering
(b) Modernization of operator working space


 