| Class |
Grade of
Inspection |
|
Main & BFP Turbine |
Control Equipment |
Heat Exchanger |
Other Pumps |
Generator |
|
|
 |
|
|
|
|
|
| A |
Complete Inspection |
|
Open upper casing. Remove rotor. Remove lower nozzle diaphragm, nozzle box and inner casing |
Disassemble each part of equipment and inspect completely. |
Remove channel cover and inspect for tube leak etc. |
Open upper casing. Remove rotor and inspect completely. |
Remove generator rotor and inspect completely |
| B |
Semi-complete Inspection |
|
Open upper casing only. Hold rotor in lower casing. |
|
|
|
Disassemble both outer end shields (upper half), do not remove rotor, and inspect. |
| C |
Simple Inspection |
|
Do not open upper casing. Overhaul steam valves only. |
Remove cover or man / hand hole and inspect |
|
|
Disassemble bearing caps only and inspect bearing. |